Happened July 2026TARGETPublished 3 August 2026Reviewed 11 August 2026

Airport reported about 80 percent complete, operations targeted for September-October 2026

After a July 2026 review by Union Civil Aviation Minister K. Ram Mohan Naidu, Dholera International Airport was reported about 80 percent complete, with operations targeted for September-October 2026 and the passenger terminal around 75 percent done.

A date or number somebody is aiming at. Not a thing that has happened.

The runway, taxiways and ATC tower were reported complete earlier in the summer, and the first calibration aircraft landed on 4 June 2026. The original December 2025 target was missed, and opening dates for this airport have slipped repeatedly since planning began, so the September-October window is a target, not a commitment.

Phase 1 is a single 3,200 m Code 4E runway built by DIACL, a joint venture of AAI (51 percent), Gujarat (33 percent) and NICDC (16 percent).

What would move this onDGCA licensing steps and a formal commissioning announcement from DIACL or the ministry. No firm opening date exists.
Where this came fromJuly 2026 press coverage of the minister's review; DIACL

If one of these links has moved or we have read it wrong, write to editor@dholerasir.news and we will fix the entry and say so on the corrections page. For how we decide what counts as confirmed, see how we source and correct. For the full dated history of the region, see the Dholera timeline. For any term above you do not recognise, see the glossary.